P1 installed the Plumbing, HVAC Piping and Sheet Metal in the Corridors and other production areas of the plant. Wing 1 Scope included four different contract areas in the building, totaling approximately 89,000 linear feet of pipe and 1.5 million lbs. of duct.
Wing 1 wrapped up in 2025, and P1 was awarded Wing 2, with a predominantly pipe scope including approximately 106,000 lf of pipe and 600,000 lbs. of duct.
Project Details
DeSoto, KS
2025 (Wing 1) 2027 (projected, Wing 2)