DST Systems Data Facility Expansion
P1 Group installed new critical power with paralleling switchgear and new generators to support DST’s functioning data center. All equipment was installed and brought online while the data center was in full operation.
P1 handled: installation of medium voltage generators, transfer switches, and associated building critical switchgear; building power, lighting and fire alarm; lightning protection, and access control systems; and live data center critical power re-configuration.
Services Provided
-
Electrical Construction
-
Controls
Project Details
Kansas City, MO
JE Dunn Construction
FEA
Steelman
Need a team of professional specialty contractors to help with your next construction project? Get started by finding a P1 Construction location near you.
Still not sure if P1 Construction, LLC is the right fit? Feel free to check out more examples of our past work and hear from our statisfied customers.