A3 Parking Garage
P1 Group completed the third parking garage at Disney Springs in the last five years.
The P1 Group Architectural Metal team recently completed another project for Disney. A3 is the third parking garage at Disney Springs the team has completed within the last five years. The $6 million project included fabrication and installation of 141,505 sq. ft. of aluminum facade in four elements: corner planters, checkered louvers, horizontal louvers, vertical tube and perforated panels. All of the aluminum sheet and extruded tube was fabricated in the Architectural Metal shop.
Quick Facts
-
Design/Build project
-
851,104 lbs of aluminum sheet and extruded tube
-
11,426 shop fabrication hours
-
13,239 field installation hours
Project Details
January, 2019
Finfrock/RCID
WL Cassell & Associates, Inc.
$6,001,784
15 Months
141,505
Need a team of professional specialty contractors to help with your next construction project? Get started by finding a P1 Construction location near you.
Still not sure if P1 Construction, LLC is the right fit? Feel free to check out more examples of our past work and hear from our statisfied customers.