Skip to main content

We're Hiring - Join the P1 Service, LLC team   View Details

Paola High School

P1’s Performance Solutions team was able to extensively performance test the system and make the neces­sary recommendation to address issues with the high school’s 30-year-old hydronic piping system.

The Variable Frequency Drives (VFDs) and the Sidestream Centrifugal Separator Filtration System were installed first so leaks would not be compounded, and existing sludge and sediment in the system would be removed.

During the brief three months of summer, P1 Service removed and replaced all the hot water piping from the mains to all the hot water terminal devices. The electric boilers were also replaced with new hybrid high efficiency natural gas boilers, which will create an annual energy cost savings of approximately $70K.

Services Provided

  • Mechanical

  • Plumbing

  • Electrical

  • Service

Project Details

Location

Paola, KS

Completion

August 2019

Owner

USD #368

System Types

Hot water heating, boilers, controls

electrical services icon
Work With Our Technicians

Do you need a team of professional technicians to help repair or maintain your facility's systems? Get started by finding a P1 Service location near you.

electrical services icon
View More Projects

Still not sure if P1 Service, LLC is the right fit? Feel free to check out more examples of our past work and hear from our statisfied customers.