P1 wins mechanical project at KU’s Center for Advanced Heart Care

KANSAS CITY, Kan. – P1 Group, Inc. has won a mechanical project for the 9th floor buildout of the Center for Advanced Heart Care at the University of Kansas Hospital in Kansas City, Kan.

P1 Group was awarded this project in July 2011 and expects to complete it by July 2012.

Scope of Work

  • Finish out of the shell space of the 30,690-square-foot 9th floor
  • Buildout of (20) patient rooms
  • Install plumbing and medical gas systems
  • Ductwork and hot water to reheat boxes

Congratulations to Jeff Peterson, estimator, for securing this work for P1 Group.

Clint Zier will manage the project.

P1 Group also built the original first six floors of the Center for Advanced Heart Care. For more information about that project, click here.