P1 secures two mechanical projects at St. Luke’s East Campus

LEE’S SUMMIT, Mo. – P1 Group has won a pair of piping and plumbing projects for the St. Luke’s East campus.

Intensive Care Unit Scope of Work

  • Tenant finish-out of 18,450 square feet of shell space
  • Chilled water, hot water, steam and condensate piping
  • Installation of (2) 23,000 CFM Air Handling Units
  • (128) Plumbing fixtures and associated domestic water, sanitary waste and vent piping
  • Medical gas piping to serve (16) head walls

5th Floor Expansion Scope of Work

  • 54,109 square feet vertical expansion to the existing hospital
  • Chilled water, hot water, steam and condensate piping
  • Installation of a new 36,000 CFM Air Handling Unit

Congratulations to the following associates who were integral in securing this work for P1 Group:

  • Joe Camren, Mechanical Estimator
  • Glenn Bartholomew, Project Engineer

Colin Fitzgerald, project engineer; Chris Lauver, plumber foreman; and Marcus Conner, pipefitter foreman, will oversee these projects.