BROWNVILLE, Neb. – P1 Group has won a series of mechanical and electrical projects for Cooper Nuclear Station (CNS).

Fire Protection Line and Hangar Support Fabrication

  • Procure (44) pipe supports for five different designs
  • (50) piping spool pieces of 4” Schedule 40 pipe – Totaling 620 linear feet
  • SMAW and Victaulic grooving, hot-dip galvanized and hydro-tested
  • This work will be fabricated in the P1 pipe fabrication facility

Project Coordinators to Support Various Projects

  • Manage the Drywell Fan Coil Replacement Project
  • Replace (4) units in two weeks
  • Coordinate and schedule work with (5) different work groups

Staff Augmentation

  • For an Electrical Maintenance Planner.

CNS is a boiler water reactor type nuclear power plant, it is the largest single-unit electrical generator in Nebraska.